8 Posts
bcooper79 started a discussion
Excavation completed Dec 27th. Footings and basement walls scheduled to start Dec 29th
    Comment
bcooper79 started a discussion
Installed tracking pad Dec 19. Excavation for basement is scheduled to begin Dec 26th, and footings / basement walls scheduled to begin Dec ... Read More
    Comment
bcooper79 started a discussion
Cut trees Dec 2nd while we wait for construction permits. Once permits are issued, we'll be ready to dig for the basement.
    Comment
bcooper79 started a discussion
Got the tree survey back Nov 11th, along with the proposed location of the house. We only need to cut six trees. Next step - exterior select... Read More
    Comment
bcooper79 started a discussion
Cleared brush Oct 26. Now we schedule the surveyor to get a tree survey and topo. Looks like we will be able to keep a lot if mature oaks.
    Comment
bcooper79 started a discussion
Closed on the lot Oct 15. Need to clear brush so we can survey trees and topo.
    Comment
bcooper79 started a discussion
Lot is cleared and ready to break ground
    Comment
bcooper79 started a discussion
Oct 15
    Comment